Vineyard Wind is suing GE Renewables, claiming turbine failures and delays led to a $853 million contract dispute that could impact a major offshore wind project serving Massachusetts.The complaint, ...
Wind turbine maker GE Vernova is paying Nantucket, Massachusetts, $10.5 million after a wind turbine blade from the Vineyard Wind 1 project snapped off and scattered debris across the island during ...
A Suffolk Superior Court judge has ruled that GE Renewables cannot abandon its work on the Vineyard Wind offshore wind farm south of Martha's Vineyard, saying the company has no legal basis to quit ...
GE Vernova’s onshore wind business announced that it received orders in 2024 to repower over 1 gigawatt (GW) of wind turbines in the US. Wind energy repowering is all about breathing new life into ...
Add Yahoo as a preferred source to see more of our stories on Google. NEW BEDFORD, Mass. (WPRI) — Nearly a year after a turbine blade failure scattered debris along the shores of Nantucket, GE Vernova ...
Projects directly support domestic manufacturing jobs at GE Vernova’s Pensacola, Florida facility Repowering allows for the rapid deployment of additional capacity by utilizing existing sites to ...
GE Vernova said it has an agreement with global energy developer RWE to provide 109 of GE Vernova’s 2.8-MW wind turbines for two projects in Texas. The new Honey Mesquite wind farm in Glasscock County ...
A Massachusetts judge has ordered GE Renewables to remain on the $4.5 billion Vineyard Wind offshore project amid a high-stakes contract dispute. The ruling stems from a 2024 turbine blade failure ...
The ruling says GE Renewables failed to challenge the finding that it was at fault for an accident in 2024, when a blade detached from a turbine and crashed into the ocean. A Massachusetts judge ruled ...